Hamilton County Road & Bridge Committee met November 19

Chairs

Hamilton County Road & Bridge Committee met Nov. 19.

Here is the agenda provided by the committee:

Call to Order – Pledge – Roll Call

Approve Minutes of Last Meeting

Recognition of Visitors

Old Business

1. Bridge Program Update:

a. South Crouch 033-3109 (HBP FY?)

i. 1 Span Estimate $200,000 

ii. On hold. 

b. Mayberry 033-3113 (TBP FY19)

i. 1 Span Estimate $240,000 

ii. In-House Design $10,500

1. Working on Hydraulic Report and Plans 

c. Crook 033-3185 (TBP FY19)

i. Slope Protection Rehab Estimate $70,000 

ii. In-House Design $8,000

1. Working on Bridge Condition Report 

d. South Flannigan New Bridge (TBP FY 19)

i. 1 Span Estimate: $140,000 

ii. In-House Design $12,500 

e. South Twigg 033-3191 (TBP FY 20)

i. 1 Span Estimate: $300,000 

ii. In-House Design $12,500 

f. Crook New Bridge (TBP FY 20)

i. 1 Span Estimate: $225,000

ii. Dees Construction $ 186,115 

iii. Scheduled to start December 1, weather permitting 

g. Dahlgren Low Water Crossing 1800N (HBP FY19)

i. 3 Span Estimate: $500,000 

ii. HLR Design $29,000 

h. Dahlgren Low Water Crossing 300E (HBP FY20)

i. 3 Span Estimate: $500,000 

ii. HLR Design $29,000 

i. Dahlgren Low Water Crossing 200E (TBP FY19)

i. 3 Span Estimate: $500,000 

ii. HLR Design Plans are approved

iii. Working on ROW

2. Road Improvement Program Update:

a. Anderson School Road 10-00108-00-FP (STR FY2020)

i. Soil Cement w/A-3 Oil & Chip (new alignment) 

ii. Construction Estimate: $675,000 

iii. Engineering: $ 45,000 

iv. STR $540,000 / State Match $135,000 

b. Dahlgren South Overlay 19-00115-00-RS (STR FY2022)

i. 2” Asphalt Overlay 1725N to State Rt 14 

ii. Construction Estimate: $850,000 

iii. Engineering: $ 15,000 

iv. STR $692,000 / State Match $173,000

3. Pavement Preservation Program:

a. 18-00113-00-PP $310,000

i. Blairsville, Blooming Grove, Walpole & Akin 

ii. Set up of FY 2021 (summer 2020)

Other Business.

a. ICC 600E/1600N Rail Safety Project

i. Updating the Environmental Review, working on Preliminary Plan and ROW plan. 

b. Multi-Year Improvements:

i. Phase I (Miller Store / Army Navy):

1. Construction is complete. ROW has been seeded and strawed. 

2. Two Items on Board Mtg Agenda. Res 2019-23 is the USDA Loan Resolution and Ordinance 07-2019 is the bonding ordinance. 

3. Getting culvert inventory together for Phase 

II. Energy Culvert will hold their price if we get them before the end of 2019. 

c. New Grader: Grader will be delivered by Tuesday 11/19. The Rental Agreement will be made at time of delivery with payment due in 30 days. We’ll pay it at the December Board meeting. 

d. Resolution to repay $40k Culvert and Bridge intergovernmental loan. 

e. Resolution to transfer funds to the Federal Aid Matching Tax Fund. We received a letter from IDOT that the 2017 FA Matching tax was less than the minimum.045% levy and we would need to transfer $2800 to this account before 11/30/19 to receive our State Matching Assistance appr. $100,000. 

f. E911 signs:

i. Finishing paperwork on RD road project and had two IDOT audits in the last month. We’ve not had time to work on signs this month.

Equipment/Maintenance Report: Tony Steele

a. Red Tandem Truck – Brakes fixed, starter switch & alternator 

Motion to Sign Claims Motion to Adjourn

https://www.hamiltoncountyillinois.com/county-board-meetings/2019/11/11-19-2019-agenda-highway-county-board-meeting/

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate