Hamilton County Road & Bridge Committee met June 21

Hamilton County Road & Bridge Committee met June 21.

Here is the agenda provided by the committee:

Hamilton County

Road & Bridge Committee Meeting

Agenda

Call to Order - Pledge - Roll Call

Approve Minutes of Last Meeting

Recognition of Visitors

Old Business

1. Bridge Program Update:

a. South Crouch 033-3109 (HBP FY?)

i. I Span Estimate $200,000

ii. On hold.

b. Mayberry 033-31 13 (TBP FY22)

i. I Span Estimate $240,000

ii. In-House Design $ I 0,500

1. Working on Hydraulic Report and Plans

2. Got Environmental update

c. Crook 033-3185 (TBP FY22)

i. Slope Protection Rehab Estimate $70,000

ii. Hutchison Engr ($12,3 14 80/20)

d. South Flannigan New Bridge (TBP FY 23)

i. 1 Span Estimate: $140,000

ii. In-House Design $12,500 pd

e. South Twigg 033-3191 (TBP FY 23)

i. I Span Estimate: $300,000

ii. Hutchison Engr ($33,848 80/20)

f. Dahlgren 04132 Low Water Crossing 300E (TBP FY22)

i. Dees Inc. $346,686

ii. Structure complete finishing up approaches

iii. We'll need to pay Dees for work complete to date when the quantities are documented and the pay application is complete.

g. Dahlgren 200E RBI Aluminum Box Culvert.

i. Energy Culvert $58,420

ii. Material delivered, summer install

2. Road Improvement Program Update:

a. Dahlgren South Overlay 19-00115-00-RS (STR FY2023)

i. 2" Asphalt Overlay 1725N to State Rt 14

ii. Construction Estimate: $850,000

iii. STR $692,000 / State Match $173,000

iv. How to proceed with design?

b. Thackeray Road Estimate $1,050,000 2022

i. Soil-Cement and Oil & Chip 6.4 miles in conjunction with ICC Grade Crossing Improvements.

ii. Local Funds & ICC Funds

c. Dale Road Estimate $825,000 State FY2024

i. Soil-Cement and Oil & Chip 4.7 miles with State RBI ($367,066) & Federal STR Funds ($457,934).

3. Pavement Preservation Program:

a. 20-00116-00-PP Chip Seal Estimate $450,000 State FY 2024

1. 36.5 miles: Piopolis+500E; Miller Store; Army Navy; Anderson School to Walpole; End of Walpole to County Line

ii. Setting up for Letting in June 2023

b. 21-00117-00-PP Chip Seal

i. Updating the PPP program. Will determine roads after program is updated.

Other Business.

a. ICC 600E/1600N Rail Safety Project

i. The Addenda Environmental Review has been submitted, Preliminary Plans and ROW plan complete.

ii. ROW Negotiations:

I. Hanson Engineering to send executed contract for County signatures and !DOT approval.

2. ROW plats and deeds are complete.

3. Title Commitments are in hand. Hanson is advising to get Title Insurance Policies, this is estimated at $1 ,500.

4. I'm trying to figure out the reimbursement process and from what I can figure it will run through our County MFT account, but I'm having a hard time getting information from anyone.

iii. ICC Agreement Extension

I. The ICC Rail Safety Program agreements include design and construction in a 2 year period. The second term will expire June 28, 2022 and we need to request another extension.

b. ICC Thackeray Road Rail Safety Project

i. The ICC has contacted me about getting estimates together for the approach work to improve this RR crossing. (no change)

c. New Highway facility:

i. Building and Grounds committee.

d. EPA UST incident:

i. There will be a closure report that will need filed in the Clerk's Office.

e. New Equipment Budget adjustment - We received the correct invoice for the Cat Excavator with difference of $133,073.04. lt was brought to my attention that even though we've purchased equipment with revenues from the surplus equipment receipts the budget line item had not been adjusted. We are ordering the new trailer and will be able to sell the old trailer. Following are recommendations that were sent to Dustin:

f. 30' Tilt Bed Trailer for excavator has been ordered from Kaufman Trailers factory direct, no trade $ 17,490+$700 (shipping), estimated build date is November.

g. E9 l I signs:

i. Aaron is estimating $12,000 for replacing Rd Name signs. Road Commissioners are willing to help replace the signs. We need to decide how to proceed.

h. County Engineer - the board needs to decide how to proceed and advertise the position.

1. Engineering Software - recommending a I-year renewal for $1 ,232.55. The renewal will be for 7/21 /22 - 7/20/23.

J. County Vehicle Policy

Equipment/Maintenance Report: Tony Steele

a. Aaron's truck has 175,000 miles and is in need of attention.

Motion to Sign Claims

Motion to Adjourn

https://drive.google.com/file/d/1y9hPWQdp_vFm6ahscwYvYtV5Bj5Tz_7p/view

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS