Hamilton County Road and Bridge Committee met May 15.
Here is the agenda provided by the Committee:
Call to Order – Pledge – Roll Call
Approve Minutes of Last Meeting
Recognition of Visitors
Old Business
1. Bridge Program Update:
a. South Crouch 033-3109 (HBP FY?)
i. 1 Span Estimate $200,000
ii. On hold.
b. Mayberry 033-3113 (TBP FY19)
i. 1 Span Estimate $240,000
ii. In-House Design $10,500
1. Working on Hydraulic Report and Plans
c. Crook 033-3185 (TBP FY18)
i. Slope Protection Rehab Estimate $70,000
ii. In-House Design $8,000
1. Working on Bridge Condition Report
d. South Flannigan New Bridge (TBP FY 19)
i. 1 Span Estimate: $140,000
ii. In-House Design $12,500
e. South Twigg 033-3191 (TBP FY 20)
i. 1 Span Estimate: $300,000
ii. In-House Design $12,500
f. Crook New Bridge (TBP FY 20)
i. 1 Span Estimate: $225,000
ii. In-House Design $12,500
g. Dahlgren Low Water Crossing 1800N (HBP FY19)
i. 3 Span Estimate: $500,000
ii. In-House Design $20,000
h. Dahlgren Low Water Crossing 300E (HBP FY20)
i. 3 Span Estimate: $500,000
ii. In-House Design $20,000
i. Dahlgren Low Water Crossing 200E (TBP FY19)
i. 3 Span Estimate: $500,000
ii. In-House Design $20,000
2. Road Improvement Program Update:
a. Anderson School Road (STR FY2020)
i. Soil Cement w/A-3 Oil & Chip (new alignment)
ii. Construction Estimate: $675,000
iii. Engineering: $ 45,000
iv. STR $540,000 / State Match $135,000
3. Pavement Preservation Program:
i. 14-00112-00-PP $400,000
1. Oil & Chip + Patching Blairsville
2. Finishing Plans and Spec’s
3. August 4th Letting
Other Business.
a. ICC 600E/1600N Rail Safety Project
i. ICC is setting up the crossing project for FY2019 budget.
ii. Discussion of the ICC Agreement and required Vacation documents. The Agreement is giving 24 months for design and construction.
iii. IDOT and FHWA are working through some paperwork issues to transfer the project from the EDP project to the Rail Safety project.
iv. Jurisdictional Transfers:
1. I will be on the agenda for the S Crouch Township meeting Monday 7/14 to discuss the ICC Agreement with them. A portion of 1600N will need to be transferred to the County so the County road will be continuous to Rt 142.
b. S. Dahlgren shoulders: tailgate spreader is in hand. We are coordinating welding the mounts on the truck and fabrication of the shoulder box.
c. Contract Mowing: Discussion of Bids received May 3rd:
i. Precision Property Maintenance LLC ($115,762)
1. NW first/second: $8,500/$21,250 = $29,750
2. NE first/second: $6,900/$17,250 = $24,150
3. SW first/second: $12,525/$31,312 = $43,827
4. SE first/second: $5,150/$12,875 = $18,025
ii. The Twisted Horseshoe & More LLC
3. SW single bid on draft bid form $18,500
d. Multi-Year Improvements: Checking on equipment rental & material costs.
Equipment/Maintenance Report: Tony Steele
a. Backhoe was down again, weld repair on boom.
Motion to Sign Claims
Motion to Adjourn